Devanahalli, Bengaluru North · Apartments
Green Valley Heights
Two towers of 2 and 3 BHK homes beside Green Valley Residency: east-facing park views, a pool deck between the towers, a clubhouse and EV-ready parking. Walk through any flat in 3D, see how far your floor has been built, and pay only as each slab is cast.
58%
Construction progress
Last update 28 Oct 2026: Tower A: 11th slab done, Tower B flooring started
55
Available
112
Total flats
₹82.7 L
From
RERA registered
PRM/KA/RERA/1250/303/PR/SAMPLE/0002
Possession promised
31 Mar 2028
Towers on site
Tower A
16 floors · 4 flats a floor · 32 of 64 available
46%
- Foundation100%
- Structure (slabs)69%
- Blockwork and plaster44%
- Electrical and plumbing25%
- Flooring and finishing8%
- Facade and paint0%
11 of 16 slabs castRoof slab ~Mar 2027Developer’s target 31 Dec 2027
Tower B
12 floors · 4 flats a floor · 23 of 48 available
74%
- Foundation100%
- Structure (slabs)100%
- Blockwork and plaster83%
- Electrical and plumbing58%
- Flooring and finishing34%
- Facade and paint25%
12 of 12 slabs castDeveloper’s target 31 Aug 2027
Floor plans
2 BHK · Type A
913 sq ft carpet · 1285 super37 available · from ₹82.7 LWalk through it in 3D
3 BHK · Type B
1326 sq ft carpet · 1860 super18 available · from ₹1.20 CrWalk through it in 3D
Pay as the building rises
A construction-linked plan: each part falls due only when that stage is built and certified.
- 1.Booking amount10%
- 2.Agreement for sale10%
- 3.On completion of foundation15%
- 4.On casting of the 4th slab10%
- 5.On casting of the 8th slab10%
- 6.On casting of the 12th slab10%
- 7.On casting of the roof slab10%
- 8.On completion of masonry10%
- 9.On flooring and finishing10%
- 10.On possession5%
Amenities
- Swimming pool
- Clubhouse with gym
- Children's play area
- Jogging track
- Indoor games
- EV charging
- 24x7 security
- Power backup
- Rainwater harvesting
- Sewage treatment plant
Construction updates
- 28 Oct 2026Project 48%Tower A: 11th slab done, Tower B flooring started
Vitrified flooring has started on the lower floors of Tower B; sample flat finishing is under way.
- 12 Oct 2026Project 42%Tower A: 10th floor slab cast
Shuttering has moved to the 11th floor. Plumbing sleeves are in up to the 8th floor.
- 16 Sept 2026Project 38%Tower B: roof slab cast
All 12 slabs of Tower B are cast. Blockwork has reached the 10th floor.