Green Valley Residency
A 6.5-acre gated plotted layout with 40 ft and 30 ft internal roads, underground drainage, a central park and a clubhouse. Sample project for the REMMO demo.
What’s been built
Construction updates
- 28 Oct 2026ClubhouseProject 55%Road started
Street lights halogen to.led
- 6 Oct 2026Internal roadsProject 53%Internal roads: wet-mix base complete
All internal roads have the wet-mix macadam base. Asphalt starts after the monsoon.
- 15 Sept 2026ClubhouseProject 47%Clubhouse foundation complete
Foundation and plinth for the clubhouse are done.
- 21 Aug 2026Storm water drainsProject 44%Drains extended to Block C
Drain lines run along both sides of the main road.
- 17 Jul 2026Street lights and cablingProject 42%First street light poles installed
Poles along the 40 ft main road are up and wired.
- 17 Jun 2026Central parkProject 38%Central park: levelling and pathways
Walkway kerbs are in. Planting starts after the monsoon.
- 18 May 2026Overhead water tankProject 37%Overhead tank: column work done
The 1 lakh litre tank columns reached full height.
- 18 Apr 2026Street lights and cablingProject 33%Underground cabling started
BESCOM-approved trenching has begun along Block C.
- 9 Mar 2026Storm water drainsProject 31%Drains complete for Blocks A and B
Culverts at both road crossings are finished.
- 8 Jan 2026Internal roadsProject 26%Granular sub-base laid on main roads
GSB layer compacted on the 40 ft roads. 30 ft roads next.
- 30 Oct 2025Storm water drainsProject 19%Storm water drains: Block A started
Precast drain sections are being placed along the main road.
- 11 Aug 2025Internal roadsProject 14%Road formation and earthwork started
Excavation and compaction for the 40 ft main road are under way.
- 13 May 2025Compound wall and gateProject 9%Compound wall complete with main gate
Wall plastered and painted on all four sides. Security cabin foundation is in.
- 19 Mar 2025Compound wall and gateProject 3%Compound wall foundation laid
Footing and plinth beam complete on the north and east sides.
Documents
Announcements
- 11 Oct 2026Open house this Sunday, 10 am to 4 pm
Walk the site with our team. A free shuttle runs from the Devanahalli bus stand every 30 minutes.
- 28 Sept 2026Next price revision on 1 January 2027
Bookings made before 31 December keep today’s price.